The City of Savannah will commence construction of a new sewer line extending from Little Neck Road through Canal Bank Road to I-95, covering approximately 6 miles along the S&O Canal.
Phase 1 of the project involves initial work at the directional drill exit. Beginning Monday, July 15, a partial lane closure will be implemented on Canal Bank Road for a short section.
Phase 2 will include the installation of the sewer pipe, requiring a full lane closure along the entire length of Canal Bank Road. This phase is scheduled for the week of July 20, subject to weather conditions and project progress. Residents will retain full access to their homes throughout the construction period.
Further updates on subsequent phases will be provided as the project advances. For inquiries, please contact Tyler Staub at Ruby-Collins, Inc. via email at [email protected] or (770) 432-2900